Main fuse / A | Zone I | Zone II |
3 x 25 A | €2,733 | €4,139 |
3 x 35 A | €3,836 | €5,789 |
3 x 50 A | €5,475 | €8,279 |
3 x 63 A | €6,903 | €10,425 |
3 x 80 A | €8,765 | |
3 x 100 A | €10,951 | |
3 x 125 A | €13,684 | |
3 x 160 A | €17,519 | |
3 x 200 A | €21,902 | |
3 x 250 A | €27,377 | |
3 x 315 A | €34,492 | |
3 x 400 A | €43,804 | |
yli 3 x 400 A | €109,00 / A | |
Zone I = The connection point is located within a local detailed plan or at a maximum distance of 250m from the current distribution substation.
Zone II = The connection point is located outside a local detailed plan or at a distance of between 250m and 800m from the current distribution substation.
In low-voltage connections, we comply with area pricing at sites that are outside the areas subject to zone pricing, i.e. the connection fee is based on direct connection costs and the capacity reservation fee.
We also do not apply zone pricing in areas where the transformer circuit has a valid clause to refund a connection fee that is higher than normal. Connections outside zone and area pricing are priced on a case by case basis.
We design the connections in accordance with normal design criteria using standard structures and normal dimensioning criteria, which we have specified in further detail in the connection fee criteria. The dimensioning criteria ensure high quality of electricity and a good level of operational safety.
We send the customer an offer for an individual connection within 5 working days and an area offer within 10 working days of receiving the request for a quote.
For increasing the main fuse of the connection, we charge an extra connection fee in the areas of zone price lists I and II. The amount of the extra connection fee is the difference of the connection fees for the old and the new main fuse size. Outside the zone area, the extra connection fee consists of the capacity reservation fee in accordance with the increased capacity.
The customer receives the right to use the connection by paying the connection fee. Kymenlaakson Sähköverkko Oy will build the electrical network required for the connection up to the connection point, which in an overhead line network is a pole or the wall of the property, and in an underground cable network it is the boundary of the plot. We specify the connection point in the connection contract. The connecting customer is responsible for the costs of changes in the connection point.
We recommend that the customer installs the metering centre outdoors or in a separate space that is accessible by Kymenlaakson Sähköverkko Oy. The metering centre must not be installed on a pole
(incl. vat 25,5%, transferable, non-refundable)
A low-power site of a maximum of 500 W, such as a billboard, amplifier, light signal or similar. The connection can be implemented without kWh metering if the site’s power consumption can be estimated in a reliable way and metering cannot be arranged within reason.
3 x 25 A | Zone I ja II | €1316 |
Value added tax at 25,5% is added to the connection fees. The connection fee is transferable, but not refundable. The connection offer is case-specific.
10 kV and 20 kV | 110 kV | |
Consumption | ||
Basic part (case-specific) | direct connection costs | direct connection costs |
Capacity reservation fee | €42kVA | €26/kVA |
Production | ||
Basic part (case-specific) | direct connection costs | direct connection costs |
Capacity reservation fee, production, over 2 MVA | €41/kVA | €25kVA |
The same principles apply for the determination of the production connection charges as for the consumption connection charges. With the exception of less than 2 MVA production equipment, for which a capacity reservation fee is deducted from the connection fee.